Transportable Rectifier Substation tGUW Zwätzen

As part of the transition to modern bi-directional low-floor vehicles, an additional rectifier substation was required near the Zwätzen track loop to ensure traction power supply. The goal was to secure the power supply for the Löbstedt–Zwätzen section and specifically increase redundancy within the Jena public transport network.

Client: Jenaer Nahverkehr GmbH
Location: Jena-Zwätzen
Period: 2023–2024

Technical Requirements

Container design: The tGUW is implemented in a walk-in, mobile container – all operations are carried out from inside. Its dimensions allow transport without special permits.

Our Services

ELPRO provided the following comprehensive services:

  • Delivery of the complete, transportable rectifier substation including medium-voltage switchgear, transformer, DC systems & secondary equipment
  • Cabling and installation of the container
  • Commissioning and integration into the existing overhead line and power supply infrastructure

Project Success & Significance

  • On-time completion in 2024 – the tGUW Zwätzen is fully operational
  • Major contribution to redundancy and grid stability in the Löbstedt–Zwätzen area
  • Significant improvement in power supply reliability

Why this project stands out for ELPRO:

  • Innovative strength: mobile, modularly designed substations
  • Electrical consistency: from container design and switchgear to final commissioning
  • Public transport infrastructure enhancement: a strategic contribution to power supply quality in Jena – serving as a model for similar transport networks