Comprehensive Reconstruction of the Substation Chemnitz / Berndorf

Chemnitzer Verkehrs-AG operates a closely interconnected network of tram and railway lines – a total of 6 tram and 38 bus routes, serving around 33.4 million passengers per year. As part of the network expansion, new rectifier substations had to be constructed.

Client: Chemnitzer Verkehrs-AG (CVAG)
Project period: 2020–2024
Location: Chemnitz (Berndorf)
Scope of work: Comprehensive reconstruction of the Berndorf rectifier substation

Scope of Services
ELPRO carried out the complete reconstruction of the Berndorf substation, including:

  • Delivery of the substation equipment, including key components such as DC switchgear, medium-voltage systems, and transformers
  • Cabling and installation within the existing substation infrastructure
  • Commissioning and coordination of technical systems to ensure smooth operation

The reconstruction was executed in accordance with the latest railway electrical engineering standards, strengthening Chemnitz’s infrastructure.

Project Completion & Added Value
The project was completed on schedule and to the full satisfaction of CVAG. Since then, the new Berndorf substation has contributed to power supply reliability and grid stability – ensuring dependable public transport operations in Chemnitz.

Result
The project showcases our expertise in comprehensive energy and plant engineering solutions for transport networks. In particular, the precise execution within a complex urban environment highlights our competence in planning, installation, and commissioning of electrical systems.